Research on The Schedule and Cost Control of Wind Turbine Blade Product Development based on Earned Value Management

Authors

  • Liyan Zhao Sinoma Wind Power Blade Co., Ltd, Beijing 100192, China
  • Shuxiang Mu Sinoma Wind Power Blade Co., Ltd, Beijing 100192, China
  • Yiwen Zhu Sinoma Wind Power Blade Co., Ltd, Beijing 100192, China
  • Yan Liu Sinoma Wind Power Blade Co., Ltd, Beijing 100192, China
  • Weisheng Liu Sinoma Wind Power Blade Co., Ltd, Beijing 100192, China
  • Yang Gao Sinoma Wind Power Blade Co., Ltd, Beijing 100192, China

DOI:

https://doi.org/10.6919/ICJE.202611_12(11).0002

Keywords:

Wind Turbine Blade; Project Management; Earned Value Management; Cost and Schedule.

Abstract

Cost, schedule and quality constitute the core objectives of project management. Accurate cost and schedule control and prediction are critical to the smooth delivery of wind turbine blade R&D projects. As the mainstream tool for integrated project control, the earned value method can identify project deviations and optimize the allocation of duration and cost. Nevertheless, the traditional earned value model ignores quality constraints, scope changes and external market disturbances, and its prediction errors tend to be amplified in long-cycle, high-uncertainty blade R&D scenarios. To address this issue, this paper combines critical path screening and secondary earned value decomposition, incorporates earned schedule dimension, Monte Carlo probabilistic risk correction and agile-predictive hybrid management philosophy, and effectively improves the prediction accuracy and control reliability of schedule and cost for wind turbine blade R&D under frequent technical iterations, material price fluctuations and supply chain disruptions.

Downloads

Download data is not yet available.

References

[1] Zhou, Y. J. (2006). Project management. China Machine Press.

[2] Wang, C. F., & Li, J. P. (2008). Introduction to modern project management. China Machine Press.

[3] Mao, J. Y. (2010). Research status and prospect of earned value method. Project Management Technology, (2), 19–23.

[4] Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.

[5] Wang, X. Q. (2011). Cost planning and control of engineering projects. China Architecture & Building Press.

[6] Chen, L. Y. (2018). Research on investment cost control of engineering projects based on contract management. China Chief Financial Officer, (3), 112–113.

[7] He, C. Q., & Ma, W. Z. (2013). Engineering project cost control. China Architecture & Building Press.

[8] Qi, A. B. (2004). Errors and solutions in project earned value analysis method. The Journal of Quantitative & Technical Economics, (5), 63–68.

[9] Zhang, L., Ji, S. L., & Hou, W. (2006). Application research of earned value method in project schedule control. Journal of Shenyang University, (2), 29–32.

[10] Yu, X. Z. (2008). Schedule deviation analysis of project secondary earned value distinguishing critical path. Modern Management Science, (6), 62–64.

[11] Ma, J. B. (2013). Applied research of project cost management based on earned-value method. Co-operative Economy & Science, (7), 34–35.

[12] Liu, G. L., Wu, Y. P., & Chen, Z. (2018). Research on CBM-earned value method for cost control of construction engineering projects. Highways & Automotive Applications, (1), 178–182.

[13] Zhang, X. Y., & Dong, X. B. (2016). Improvement of cost prediction for earned-value method. Economic Research Guide, (9), 91–93, 194.

[14] Mayo-Alvarez, L., Alvarez-Risco, A., Del-Aguila-Arcentales, S., Sekar, M. C., & Yáñez, J. A. (2022). A systematic review of earned value management methods for monitoring and control of project schedule performance: An AHP approach. Sustainability, 14(22), 15259. https://doi.org/10.3390/su142215259

[15] Anbari, F. T. (2012). The earned schedule. In PMI® Research and Education Conference. Project Management Institute.

[16] Zhang, Y., Zhang, H., & Wang, H. (2024). Multi-level digital model of dynamic earned value management for complex engineering projects and its applications. Journal of System Simulation, 36(4), 835–846.

[17] Nizam, A., & Elshannaway, A. (2019). Review of earned value management (EVM) methodology, its limitations, and applicable extensions. Journal of Management and Engineering Integration, 12(1), 59–70.

[18] Li, M., & Zhou, K. (2024). Research on optimization of multi-level earned value method in power engineering project cost management. Electric Power Engineering Technology, 43(6), 212–219.

[19] Pourrahimian, E., Salhab, D., Hamzeh, F., & AbouRizk, S. (2024). The need for a multidimensional project control perspective. Journal of Construction Engineering and Management, 150(12), 04024169. https://doi.org/10.1061/JCEMD5.CENG-16435

[20] Wang, L. (2025). Research on dynamic management of engineering project cost based on earned value analysis. Construction Management, (1), 78–82.

[21] Wang, C., Tang, Y., Kassem, M. A., Ong, H. Y., Yap, J. B. H., & Ali, K. N. (2022). A novel quality-embedded earned value performance analysis tool for sustainable project portfolio production. Sustainability, 14(13), 8174. https://doi.org/10.3390/su14138174

[22] Selvaraj, Y., & Paramasivam, S. K. (2026). Integrating Monte Carlo simulation and digital twin technology for advanced risk management in fast-track infrastructure projects. Journal of Civil Engineering and Management, 32(4), 534–547.

[23] Borkar, S. K. (2025). Blending agile and earned value management for program governance. World Journal of Advanced Engineering Technology and Sciences, 16(1), 678–688.

[24] Saraireh, I., Almashaleh, H., & Al Smadi, T. (2026). Integrating artificial intelligence with earned value management for enhanced performance in smart renewable energy projects. International Journal of Advances in Soft Computing and Its Applications, 18(2), 17–38.

[25] Cai, W. Q., Huang, D., & Ye, W. M. (2023). Improved earned value management method based on Monte-Carlo simulation and critical index. Journal of Systems Engineering, 38(2), 245–253.

[26] Zhan, W., & Yang, C. (2024). Optimization of project completion prediction based on Monte-Carlo simulation and earned value analysis. Science and Technology Management Research, 44(8), 210–217.

[27] Luong, K. S., & Doan, N. (2025). Probabilistic forecasting of project cost and schedule using earned value management and Monte Carlo simulation. International Journal of Marine Science and Technology, 1–7.

Downloads

Published

2026-11-15

Issue

Section

Articles

How to Cite

Zhao, L., Mu, S., Zhu, Y., Liu, Y., Liu, W., & Gao, Y. (2026). Research on The Schedule and Cost Control of Wind Turbine Blade Product Development based on Earned Value Management. International Core Journal of Engineering, 12(11), 12-28. https://doi.org/10.6919/ICJE.202611_12(11).0002