Research on Dynamic Control of Construction Schedule in Civil Engineering based on BIM Technology

Authors

  • Yanpei Li Zhengzhou Business University, Gongyi, 451200, China;Zhengzhou Low-Altitude Economy Smart Infrastructure Monitoring Engineering Research Center, Gongyi, 451200, China;Zhengzhou Solid Waste-Based Geotechnical Reinforcement Materials Engineering Research Center, Gongyi, 451200, China

DOI:

https://doi.org/10.6919/ICJE.202609_12(9).0001

Keywords:

Building Information Modelling (BIM); Civil Engineering; Construction Schedule; Dynamic Control; 4D Simulation; Earned Value Management.

Abstract

Schedule overruns have been a problem for a long time in civil engineering projects, and the traditional, document-based management mode is no longer suitable for the uncertainties of modern construction sites. Building Information Modelling (BIM) provides a good path forward for moving schedule management from post-event reporting to continuous, model-driven control. Research has been conducted on how to incorporate BIM into all links of construction schedule management and build a closed-loop dynamic control system. Based on the above review of related studies, a three-tier structure has been proposed: a data layer, a model layer and an application layer; the 4D BIM model will serve as the information hub connecting the baseline schedule, field progress data and corrective decision-making. The first two enabling technologies are 4D construction simulation and multi-source progress data collection; the third is BIM-integrated earned value analysis and deviation-driven schedule re-optimisation. Then, the above framework will be applied to a high-rise office building project. According to the case study, after introducing BIM-based dynamic control, the schedule performance index increased from 0.82 in the third month to 1.00 at the end of the project; the frequency of progress coordination meetings dropped by about 40%, and the project was completed on schedule despite serious initial delays. Based on the above analysis, BIM can be employed to establish a closed-loop schedule control system; however, problems such as data standardisation, model granularity and organisational preparedness still need to be solved.

Downloads

Download data is not yet available.

References

[1] Azhar, S. (2011). Building information modeling (BIM): Trends, benefits, risks, and challenges for the AEC industry. Leadership and Management in Engineering, 11(3), 241–252.

[2] Barlish, K., & Sullivan, K. (2012). How to measure the benefits of BIM-A case study approach. Automation in Construction, 24, 149–159.

[3] Braun, A., Tuttas, S., Borrmann, A., & Stilla, U. (2015). A concept for automated construction progress monitoring using BIM-based geometric constraints and photogrammetric point clouds. Journal of Information Technology in Construction, 20(5), 68–79.

[4] Bryde, D., Broquetas, M., & Volm, J. M. (2013). The project benefits of building information modelling (BIM). International Journal of Project Management, 31(7), 971–980.

[5] Cao, D., Wang, G., Li, H., Skitmore, M., Huang, T., & Zhang, W. (2015). Practices and effectiveness of building information modelling in construction projects in China. Automation in Construction, 49, 113–122.

[6] Chen, K., Lu, W., Peng, Y., Rowlinson, S., & Huang, G. Q. (2015). Bridging BIM and building: From a literature review to an integrated conceptual framework. International Journal of Project Management, 33(6), 1405–1416.

[7] Eadie, R., Browne, M., Odeyinka, H., McKeown, C., & McNiff, S. (2013). BIM implementation throughout the UK construction project lifecycle: An analysis. Automation in Construction, 36, 145–151.

[8] Eastman, C., Teicholz, P., Sacks, R., & Liston, K. (2011). BIM handbook: A guide to building information modeling for owners, managers, designers, engineers and contractors (2nd ed.). Wiley.

[9] Ekanayake, B., Wong, J. K. W., Fini, A. A. F., & Smith, P. (2021). Computer vision-based interior construction progress monitoring: A literature review and future research directions. Automation in Construction, 127, 103705.

[10] Golparvar-Fard, M., Peña-Mora, F., & Savarese, S. (2009). D4AR-A 4-dimensional augmented reality model for automating construction progress monitoring data collection, processing and communication. Journal of Information Technology in Construction, 14, 129–153.

[11] Golparvar-Fard, M., Peña-Mora, F., & Savarese, S. (2015). Automated progress monitoring using unordered daily construction photographs and IFC-based building information models. Journal of Computing in Civil Engineering, 29(1), 04014025.

[12] Sacks, R., Koskela, L., Dave, B., & Owen, R. (2010). Interaction of lean and building information modeling in construction. Journal of Construction Engineering and Management, 136(9), 968–980.

[13] Sacks, R., Radosavljevic, M., & Barak, R. (2010). Requirements for building information modeling based lean production management systems for construction. Automation in Construction, 19(5), 641–655.

[14] Succar, B. (2009). Building information modelling framework: A research and delivery foundation for industry stakeholders. Automation in Construction, 18(3), 357–375.

[15] Pučko, Z., Šuman, N., & Rebolj, D. (2018). Automated continuous construction progress monitoring using multiple workplace real time 3D scans. Advanced Engineering Informatics, 38, 27–40.

Downloads

Published

2026-09-20

Issue

Section

Articles

How to Cite

Li, Y. (2026). Research on Dynamic Control of Construction Schedule in Civil Engineering based on BIM Technology. International Core Journal of Engineering, 12(9), 1-11. https://doi.org/10.6919/ICJE.202609_12(9).0001