Development and Strength Verification of Hydraulic Power Tongs for Strongly Bonded Oil Tubing Makeup and Breakout

Authors

  • Wei Luo
  • Ning Lai
  • Li Wang
  • Gang Yin
  • Lei Yang
  • Lumei Huang
  • Shasha Jia
  • Xiaolin Luo

DOI:

https://doi.org/10.6919/ICJE.202506_11(6).0001

Keywords:

Strongly Bond Tubing Buckle; Breakout; Hydraulic Power Tong; Strength Verification.

Abstract

With the development of oil and gas fields extending to deep wells, ultra-deep wells and complex formations, the bonding phenomenon of tubing buckles is becoming more and more serious. The traditional hydraulic shackle pliers are difficult to meet the demand of high torque, and the knocking auxiliary shackle has high risk and high labor intensity. For this reason, this paper designs a release power tong that can squeeze the strong bonding tubing buckle. By squeezing the strong bonding tubing buckle, the bonding force of the tubing buckle is reduced to solve the difficult problem of strong bonding tubing buckle release. The correctness of the scheme is verified by the experiment of tubing extrusion and unloading, and the extrusion load is determined to be 25 t. The structure of the extrusion device was designed, and the strength verification and structural optimization were carried out by finite element method to verify its feasibility. This study not only improves the unloading speed and unloading efficiency of strongly bonded tubing buckles, but also is of great significance to ensure the safe production of oil and gas fields.

Downloads

Download data is not yet available.

References

[1] Wang Q, Gao G. Research on the automatic shackle device of mechanized hydraulic oil pipe. Machine Design and Manufacturing Engineering, 2018, 47(7): 69-71.

[2] Geng Y, Gu Q, Sun L, Wang T. A Device Design of Automatic Remote Control Hydraulic Tubing Pincers for Screwing. Machinery Design & Manufacture, 2015, (12): 147-149.

[3] Li X, Tian M, Yang C, Liu Y, Cui Y, Huang Q, et al. Discussion on Present Situation and Development Trend of Hydraulic Power Tongs Calibration Technology for Tubing String. Petroleum Instruments, 2023, 9(6): 50-53.

[4] Zhao J, Sun P, Lou H, Wang H. Design and Calculation of Grip Opening in Hydraulic Tube Tongs. Oil Field Equipment, 2010, (01): 69-71.

[5] Liu Y, Wang J. Research on the construction of daily operation and maintenance system of oil drilling hydraulic power clamp. Plant Maintenance Engineering, 2013, (12): 110-112.

[6] Tang S. Analysis of power clamp jaw clamping mechanism. Oil Field Equipment, 1978(3): 1-16.

[7] Yang M. Installation conditions of power clamp jaw gear transmission. Oil Field Equipment, 1977(4): 28-34.

[8] Yang Y, An Q, Wang X. Development and application of dual-purpose power clamp for drill pipe and casing. China Petroleum Machinery, 2010(9): 49-51,88.

[9] Yu P. Research and design of the D60-380 hydraulic power tongs. Northeast petroleum university, 2012.

[10] Zhu M, Li Z, Yang Y, Ma X, Li Y. Development of NTQ248-25Y Toothless Casing Power Tong. Oil Field Equipment, 2023, 52(1): 31-37.

[11] Huang J, Shu S, Sun Q, Han S, Wang H. Development and Application of the WTQ245-N Micro-tooth Mark Casing Tong. China Petroleum Machinery, 2012(8): 60-64.

[12] Chen M, Guo D, Fu Q, Weng W, Baio X, Yang J, et al. Design and Analysis of Telescopic Automatic Wellhead Device for Make-up and Break-out. Drilling & Production Technology, 2024, 47(1): 138-143.

[13] Han Y, Ju Y, Luo Y, Liang W, Zhao M, Fu A, et al. Analysis on Corrosion Perforation Failure on New N80 Tubing. Materials Protection, 2020, 53(11): 160-165.

[14] Zhong B, Chen Y, Meng F, Ai F, Gao P, Li L et al. Perforation Failure Analysis of N80 Pipe. Corrosion and Protection, 2018, 39(8): 647-650.

[15] Zhao G, Lv X, Han Y. Analysis of the Reason on Tubing Corrosion Failure. Journal of Materials Engineering, 2010, (3): 51-55.

[16] Zhang X, Lin X, Feng F, Zhou M, Li S, et al. Failure Analysis of Corrosion Perforation of Tubing in Shengli Oilfield. Petro-Chemical Equipment, 2019, 48(6): 6-11.

[17] Wang L, Lv X, Zhang Z, Zhang J, Zhang S. Failure Analysis of Fractured Tubing. Corrosion & Protection, 2014, 35(3): 302-305.

Downloads

Published

2025-05-28

Issue

Section

Articles

How to Cite

Luo, W., Lai, N., Wang, L., Yin, G., Yang, L., Huang, L., Jia, S., & Luo, X. (2025). Development and Strength Verification of Hydraulic Power Tongs for Strongly Bonded Oil Tubing Makeup and Breakout. International Core Journal of Engineering, 11(6), 1-10. https://doi.org/10.6919/ICJE.202506_11(6).0001